Infrastructure Works for OBHUR PARK PROJECTt
Jeddah, KSA
Supplying materials for the infrastructure of the Qiddiya Coast
Jeddah, KSA
Building villas in the Taj Al-Maseef project
Taif, KSA
Development of schemes and infrastructure
Jeddah / Makkah, KSA
some of our projects
Project Name | Earthworks In Madinah Haramain High-Speed Railway.
Owner | Parros Obras Company.
Contract Value | 35,316,559 SAR Duration 24 Months.
Scope of Work | Earthwork (Cutting and Backfilling).
Project Name | Al Mashaaer Al Mugaddassah Metro Project – Southern Line.
main contractor | China Railway 18 Bureau Group Co.
Contract Value | 450,000,000 SAR. Duration 24 Months
Scope Of Work | Earthworks (Cutting & Backfilling) And Rock Bolt And Asphalt.
Project Name | Group Eight Project – In Holy Makkah.
Owner | Ministry of Transportation (MOT).
Contract Value | 118,315,735 SAR. Duration 36 Months.
Scope of Work | Connection of Haddah/Aljamoum Road with Jeddah South Ring Road.
Project Name | Asphalt, Road borders and lighting for Taif City and Taif Villages (Phase 2).
Owner | Municipality of Taif.
Contract Value | 46,000,355 SAR Duration 24 Months.
Scope of Work | Asphalt, Road borders, and lighting.
Project Name | Ward off the dangers of flooding and storm water.
Owner | Municipality of Taif.
Contract Value | 22,991,000.00 SAR Duration 16 Months.
Scope of Work | Construction Of Open Chanel 1.4 Km Construction Of Box Culvert 1Km.
Project Name | Dualization of Almahani/Oshairah (Phase 1) 14Km.
Owner | Ministry of Transportation (MOT).
Contract Value| 49,999,998 SAR Duration 36 Months.